Most problems have a simple cause and you can check it in a couple of minutes. Start with what you are seeing, and if it is not one of these, we are one email or one call away.
Already installed and something is wrong. Each one opens the checks that resolve most calls, and the route to us if they do not.
Almost every total outage shows at the inverter. Note the status light or the code on the screen exactly as it appears, and photograph it. That one photo is usually the difference between one exchange with us and four.
There is an AC isolator and a DC isolator, usually near the inverter. Both need to be on. If either has been switched off, by anyone, the system stops.
Look for a tripped breaker or RCD on the solar circuit. If it trips again after you reset it, stop there and contact us rather than resetting it repeatedly.
Send us the code from the inverter screen and your postcode. If the fault is in the inverter or battery, the manufacturer holds that warranty and we will take it up with them with you.
Output moves with the time of year and the cloud. A quiet week in winter is normal and not a fault.
A tree, a new extension, a neighbour’s aerial. Shade on one panel can pull a whole string down, and it moves through the day.
If your inverter reports per string, compare them. One string far below the other is a real fault and worth reporting.
A sudden drop with no weather to explain it, or generation stopping at the same time every day. Both have causes we can find.
The app reports through your home broadband. When it goes quiet the usual cause is a changed WiFi password or a replaced router, not anything on the roof. The system keeps generating while the app is offline.
Most inverters rejoin from their own screen or app. If you have changed your router or password since the install, that is the thing to redo.
If the inverter shows normal generation, this is a monitoring problem, not a system problem. Call us and we will talk you through the reconnection.
Stop, isolate if it is safe to do so, and call us on 0800 999 1454. Do not wait for an email reply.
The panels, inverter and battery carry the manufacturer warranty. The installation, the mounting and the wiring are ours. If you are not sure which one you have, ask us and we will work it out rather than send you in a circle.
Contact us and we will tell you honestly whether we can help. We need to know what is on the roof and who fitted it before we can say, and there are cases where the original installer or the manufacturer is the right route.
Email reaches the same team that answers the phone. Include your postcode, roughly when the system went in, and a photo of the inverter screen if there is a code on it. It is the difference between one exchange and four.
From the deposit to grid approval, in the order it happens. The paperwork one is worth reading first: it is the most common cause of a delay.
Your deposit books the job and locks your quote at the price you accepted. The balance is due after installation, not before.
The same person stays with your job from here through to handover, so you are not re-explaining it to someone new each time.
There is a 14 day cancellation right under the Consumer Contracts Regulations.
We ask you for two small pieces of paperwork, then book your site assessment. Those two things are what unblock everything else.
It lets us speak to your network operator on your behalf. We cannot apply for your grid connection without it.
We need the MPAN number from it, which identifies your supply point to the network operator. A photo of the bill is enough.
Without these two your grid application cannot start, and that is the single most common cause of a delayed installation. Two minutes here saves weeks later.
Your roof measurements, your loft, and your fuse board, so the system is designed around your house rather than an aerial photograph.
Be at home, and clear access to your loft hatch and your fuse board. That is all.
Around 45 minutes to an hour. your site visitor photographs the roof and the electrics. There is no power interruption.
In most cases nothing changes and there is nothing for you to do.
You get a revised quote before anything else happens, and your deposit stays refundable. We tell you first, you decide.
Your network operator has to approve the connection before we can install. Smaller systems go through G98, larger ones through G99.
Usually 10 to 45 working days depending on the operator. It is their queue, not ours, and it cannot be expedited.
We submit it, chase it weekly, and tell you when the position changes. Once your paperwork is in there is nothing more needed from you.
In most cases solar panels on a residential property are considered permitted development and do not require planning permission, as long as specific criteria are met.
Listed buildings and homes in conservation areas are the usual ones. It is worth checking with your local planning authority, and we will tell you if we think yours needs it.
Larger ground-mounted arrays and commercial roofs have their own thresholds. Ask us and we will tell you which applies to your site.
The scaffolding, the day itself, and the certificates you will need for your export tariff.
Scaffolding goes up a few days before the installation and comes down once the work has been signed off, usually within two days after. It takes about half a day to erect.
Move any cars off the driveway the night before, and unlock side access if the scaffolders need to get round the back.
Your scaffolder contacts you directly if access is a problem.
One to two days for most homes. The team fits the panels, the inverter and the battery, and commissions the system before they leave.
We need to isolate the supply while we connect the system. It is around an hour, and we will tell you before we do it.
Someone over 18 at the property, and a clear space near the fuse board for the inverter and battery.
The team tests everything and shows you how the system works and where to see your generation.
Issued within 10 working days of the installation. Check that the system specifications match what was installed and that the property address is right.
The MCS certificate is what an export tariff application asks for. Setup typically takes 2 to 4 weeks once your certificate, smart meter and export MPAN are in place, and you do not need a battery to qualify.
Your certificate, grid approval and warranty pack are what a future claim or a house sale will ask for.
Email us with your postcode and roughly when the system went in and we will resend what we hold.
Include your postcode, roughly when the system went in, and a photo of the inverter screen if there is a code on it. That is usually enough to answer you in one reply.
Both reach the same team, the one that fitted your system.
If the panels are generating but the inverter or battery reports a fault, the manufacturer holds the warranty on that unit and can often resolve it over the phone. Contact them directly, or contact us and we will do it with you.


GivEnergy Ltd, the manufacturing company, is in administration. Christopher Brooksbank of CB Business Recovery was appointed on 9 April 2026.
The support line and website above were both still operating when we checked them on 11 August 2026, as was the GivEnergy customer portal. A warranty claim against a company in administration is not guaranteed to be met, so if yours is refused or goes unanswered, tell us.
Your battery keeps working either way. We service, maintain and repair existing GivEnergy systems. Call 0800 999 1454 or email support@solar4good.co.uk.
More detail in our guide, GivEnergy Administration 2026.
If we got it right, or if we did not, we would rather hear it. Email us at support@solar4good.co.uk or leave it publicly.
When it comes to making the switch to solar energy, choosing the best solar panel installation company is crucial. The best solar panel installation company will not only provide you with top-notch service but also ensure that your investment in solar power pays off in the long run. With the help of the best solar panel installation company, you can take a significant step towards a more sustainable future while enjoying the peace of mind that comes with working with experts in the field.
our MCS-registered installers carry out every installation, so the people who answer are the people who know the system.